This concrete calculator estimates the volume and weight needed for slabs, footings, columns, tubes, curbs and stairs, then converts it to 60 lb or 80 lb bags.

Slabs, Square Footings & Walls

How many identical slabs or walls.

How to use the Concrete Calculator

Pick the shape that matches what you are pouring, then enter each dimension and choose its unit. You can mix units freely, so a slab can be 10 feet long and 4 inches thick without converting anything yourself.

Use Quantity for identical pours: four deck footings of the same size means a quantity of 4 rather than four separate calculations. Fractions are accepted, so 5 1/2 and 5.5 both work.

Concrete formula

Every shape reduces to a volume, which is then converted to cubic yards, cubic feet and cubic metres.

ShapeVolume
Slab, square footing or walll × w × h × qty
Hole, column or round footingπ × (d ÷ 2)² × h × qty
Circular slab or tubeπ × [(d₁ ÷ 2)² − (d₂ ÷ 2)²] × h × qty
Curb and gutter barrier[(curb depth × curb height) + (flag thickness × (gutter width + curb depth))] × length × qty
Stairswidth × [run × rise × n(n−1) ÷ 2 + platform depth × n × rise], where n is the number of risers

Weight and bag counts assume pre-mixed concrete at 133 lb/ft³ (2,130 kg/m³):

  • weight = volume × density
  • bags = total weight ÷ bag weight (60 lb or 80 lb)

Worked example

A patio slab 10 ft × 10 ft at 4 inches thick:

  • Convert the thickness: 4 in ÷ 12 = 0.333 ft
  • Volume: 10 × 10 × 0.333 = 33.33 ft³
  • Cubic yards: 33.33 ÷ 27 = 1.23 yd³
  • Weight: 33.33 × 133 = 4,433 lb
  • 80 lb bags: 4,433 ÷ 80 = 56 bags

At that size, ready-mix delivery is usually cheaper and far less work than mixing 56 bags by hand.

What the result means

The headline figure is cubic yards, because that is how ready-mix concrete is ordered and priced in the United States. Suppliers normally sell in quarter-yard increments with a minimum load, so round up to the next quarter yard when you place the order.

The bag counts are for pre-mixed bags from a home centre. They are practical up to roughly half a cubic yard; past that, a mixer truck is almost always the better call.

Common mistakes

  • Ordering the exact number. Add 5 to 10 percent for spillage, uneven subgrade and over-excavated footings. Running short mid-pour creates a cold joint.
  • Mixing up thickness units. A slab entered as 4 feet thick instead of 4 inches gives twelve times too much concrete. Check the unit dropdown next to each field.
  • Forgetting quantity. Eight deck footings need a quantity of 8, not one footing calculated once.
  • Ignoring subgrade variation. A slab poured over soft ground settles into low spots and consumes more concrete than the nominal thickness suggests.

Frequently asked questions

How many 80 lb bags of concrete are in a cubic yard?
How much concrete do I need for a 10×10 slab?
How much extra concrete should I order?
How thick should a concrete slab be?
Does this calculator include waste?
What does concrete weigh per cubic foot?

Sources and assumptions